Ghataprabha Valley Development Scheme Ghataprabha Project

The Work included in this Project forms an integral part of the GHATAPRABHA VALLEY DEVELOPMENT SCHEME, which is one of the major Irrigation Schemes taken up for execution by the GOVERNMENT OF KARNATAKA. The Project in brief, envisages the formation of a Reservoir by constructing DAM about 60m High and about 10,000m Long (including Dykes) across the Ghataprabha River near Hidkal Village in the Hukkeri Taluka of Belgaum. District. The gross capacity of the Reservoir is about 51 TMC. The water thus impounded in the Reservoir is proposed to be utilized for Irrigation.

The Kadabagatti Tunnel is constructed on the Right Bank Canal through Kadabagatti Hills. The total length of the Tunnel is about 6.09 kms. (including Approach and Exit Cuts).

The KABBUR TUNNEL is on CHIKKODI RIGHT BRANCH CANAL. The Tunnel site is situated near Kabbur Village in Taluka Chikkodi of Belgaum District. The length of the Tunnel is 4.01 kms. (Including Approach and Exit cuts).


Kabbur Tunnel

L - Section of Kabbur tunnel

SALIENT FEATURES KABBUR TUNNEL KADABAGATTI TUNNEL
*Location KABBUR VILLAGE, Chikkodi Taluka, Dist. Belgaum. Karnataka State. On G.R.B.C.C. Canal near Kadabagatti Village, Gokak Taluk, Dist. Belgaum, Karnataka State.
*Chainage a) Approach cut Ch. 37+110 to 37+510 (400m)
b) Tunnel Proper Ch. 37+510 to 40+825 (3315m)
c) Exit Cut Ch. 40+825 to 41+1 25 (300m)
From 21580 to 24000m
*Length of Tunnel 3315m 2230m
*Tunnel Section Standard 'D' Shape of 3.2m Diameters. Horse Shoe Shape 5.2m in 0
*Full Supply Depth 2.58m 4.264m
*Required Discharge 391.5 cusecs -
*Designed Discharge 490 cusecs. 66.28 cumecs
*Bed fall in Approach & Exit Cut. 1 in 2000 -
*Bed fall in Tunnel 1 in 1000 1 in 651.21
*Velocity developed in Tunnel 1.86m/Second 3.342 m/sec
*Location of Shaft 1) At ch. 39 + 120 "Depth 43m."
2) At ch. 40+160 "Depth 42m."
at ch. 22605m Depth 59.86m
*Irrigation command area beyond Tunnel. - 3 Lakh Acres.

QUANTITIES
*Open Excavation a) Hard Strata 78755 cum
b) Soft Strata 57203 cum
-
*Tunnel Excavation 38,729 cum 43,403 cum
*Masonry - 1,585 cum
*Concrete 24,239 cum 24,398 cum
*FINANCIAL OUTLAY (1990 S.R.) Rs. 993 Lakhs Rs. 823 Lakhs.
*Period of Performance 1986 to 1996. 1987 to 1996.

Plan & L - Section of Kadabagatti Tunnel

Kadabagatti tunnel